Implementation Status:
1.Component A: Early warning dissemination systems
ØThe State appointed “The Telecommunication Consultant India Limited (TCIL)” as the technical consultant for the preparation of DPR , Bid documents, Procurement, Implementation, Supervision, Testing, Commissioning and Training for a consultancy fee of Rs 1.73 cr.
ØTender floated for the “ Design, Supply, Installation, Testing, Commissioning, and Services of Early Warning Dissemination System (EWDS) and its of Last Mile Connectivity for the State covering all 14 districts.
ØThe Detailed Project Report (DPR) amounting Rs 66.83 cr. ( against a sanctioned amount of Rs.15.00 cr.) furnished by TCIL. Out of this NDMA has consented to provided Rs. 59.00 cr. and balance Rs. 7.83 cr. is AMC and is to born by the State.
Technical Design for Component A
Implementation Status:
- Component B: Cyclone Risk Mitigation Infrastructure
No |
Name of MPCS |
Plinth Area m2/ft2 |
Capacity |
Awarded Sum |
Name of Contractor |
Commencement date |
Completion date |
Current Stage |
1. |
Mararikulam North, Cherthala (Revenue land) |
830 m2 /8930 ft2 |
700-900 |
₹ 3,53,88,736.00 |
J & J Associates |
26-10-2018 |
29-07-2020 |
Completed |
2. |
Kathiroor/Ponniam, Kannur (Revenue land) |
975 m2 /10491 ft2 |
800-1000 |
₹ 3,19,99,735.00 |
Thomas Kannanthanam |
05-03-2019 |
30-02-2021 |
Completed |
3. |
Pullur/Hosdurg, Kasargode (Revenue land) |
975 m2 /10491 ft2 |
800-1000 |
₹ 3,28,28,418.00 |
V K Manojan |
21-06-2019 |
10-12-2021 |
Completed |
4. |
Koipady / Kumbla, Kasargode (Education land) |
819 m2 /8812 ft2 |
650 850 |
₹ 2,17,26,319.00 |
U K Mohammed |
21-06-2019 |
27-02-2021 |
Completed |
5. |
Kannur / Chalad, Kannur (Education land) |
975 m2 /10491 ft2 |
800-1000 |
₹ 3,05,55,448.00 |
T P Prakashan |
21-06-2019 |
21-10-2021 |
Completed |
6. |
Kudlu / Madhur GP , Kasargode (Revenue land) |
862 m2 /9275 ft2 |
750-950 |
₹ 2,58,24,353.00 |
Mohammed Haneef |
21-06-2019 |
21-10-2021 |
Completed |
7. |
Thazhava , Kollam (Revenue land) |
877 m2 /9436 ft2 |
750-950 |
₹ 3,03,81,491.00 |
Ismail Kutty |
01-09-2019 |
21-02-2021 |
Completed |
8. |
Palappetty ,Malappuram (Education land) |
735 m2 /7908 ft2 |
600-800 |
₹ 1,89,46,684.00 |
Musthafa K T |
01-09-2019 |
28-09-2021 |
Completed |
9 |
Vettom/ Paravanna ,Malappuram (Education land) |
1072 m2 /11534 ft2 |
900-1100 |
₹ 2,86,63,680.00 |
Musthafa K T |
01-09-2019 |
28-09-2021 |
Completed |
10 |
Azhikode, Thrissur (Revenue land) |
742 m2 /7983 ft2 |
600 – 800 |
₹ 2,91,48,736.00 |
Rasheed C |
01-09-2019 |
02-10-2021 |
Completed |
11 |
Thuruthipuram, Ernakulam (Education land) |
995 m2 /10706 ft2 |
800 – 1000 |
₹ 5,56,84,243.00 |
Rasheed C |
01-09-2019 |
01-04-2022 |
Completed |
12 |
Pallipuram, Ernakulam (Revenue land) |
903 m2/9716 ft2 |
750 – 950 |
₹ 4,58,10,409.00 |
Johnson K A |
01-09-2019 |
04-08-2022 |
Completed |
13 |
Kadappuram, Thrissur (Revenue land) |
877 m2 /9436 ft2 |
750 – 950 |
₹ 3,34,78,294.00 |
Johnson K A |
01-09-2019 |
30-06-2023 |
Structure Completed. Finishing work in progress |
14 |
Cheruthana, Alapuzha (Education land) |
998 m2 /10738 ft2 |
800-1000 |
₹ 6,05,47,598.00 |
J & J Associates |
01-09-2019 |
07-01-2022 |
Completed |
15 |
Kumarapuram, Alappuzha |
903 m2/9716 ft2 |
1100-1400 |
₹ 3,40,80,252.00 |
Ismail Kutty |
07-12-2020 |
26-10-2022 |
Completed |
16 |
Muttathara, Thiruvananthapuram |
862 m2/9355 ft2 |
1000 – 1300 |
₹ 4,86,45,338.00 |
Engineers Associates |
08-10-2020 |
31-12-2022 |
Completed |
17 |
Kasaba, Kozhikode |
975 m2/10491 ft2 |
1150-1500 |
₹ 4,01,57,300.00 |
Musthafa K T |
27-10-2020 |
14-03-2023 (Expected Date to Complete |
Structure Completed. Finishing work in progress |
|
Total |
15,343 m2 / 1,65,164 ft2 |
16,000 to 20,350 people |
₹ 60,46,67,034.00 |
|
|
|
|
Implementation Status:
Public Consultation Conducted : Public Consultations were conducted at each site locations to document the views and feedback on the project proposal to consider, during the planning stage. Details
Implementation Status:
|